Serajuddin and Chowdhury: Towards a novel approach to improve drinking water quality at Dhaka, Bangladesh

Abstract

The river water source of Saidabad Surface Water Treatment Plant at Dhaka, Bangladesh, is deteriorated too much to be treated by conventional treatment process due to excessive ammonia pollution. In order to improve the raw water quality before it enters into the main treatment chain, a pilot study was conducted for pre-treatment of the raw water. The objective is to investigate the rate of reduction of ammonia using the Meteor pilot, a biological pretreatment system, which is a laboratory scale Moving Bed Biofilm Reactor with a nominal volume of hundred liters, filled with 50 L of Meteor 660 media. The reduction of ammonia was quite significant on average 73%, while the reduction of COD was in a range from 20 to 60%. The Meteor pilot was able to treat and nitrify the raw water and produce an effluent that respects the guarantee of ammonia < 4.0 mg NH3-N/L when the raw water ammonia concentration was < 15 mg NH3-N/L. The study identified operating parameters necessary to achieve the desired goal of adequate ammonia removal. The study results would benefit a range of systems across the country by providing guidance on the design and operation of a biological pre-treatment system for ammonia removal.

1. Introduction

Dhaka, the capital of Bangladesh, at present with a population of 15 million, is almost 78% dependent on groundwater for its drinking water. The city water Authority in 2004, could supply around 1,950 million liters per day (MLD) of water, out of which 87% coming from the unsustainable underground source. Once, presumably cheap and abundant, groundwater source inside Dhaka has gradually been depleted so much that no further large extraction is possible technically and economically. There is no other way out but switch over to surface water source. As an inevitable corollary, the water authority has planned to shift at least 50% of extraction of total supply to surface water sources and accordingly actions are underway for implementing surface water treatment plants [13].
Saidabad Water Treatment Plant (SWTP) phase I was constructed with a capacity of 225 MLD, the largest water treatment plant in the country and put into operation on July 27, 2002 [4]. The Sitalakhya River at the eastern periphery of Dhaka city is the source of raw water for the SWTP (Fig. 1). A replication of a similar plant with the same size and design is underway for the second phase, where the third phase of 450 MLD of water is postulated in near future [1].
Sitalakhya River is now facing serious problems due to man-made pollution. In the dry season, there are complaints of bad smell and colour in the supplied treated water extracted from the Sitalakhya. Over viewing at the available data and the complex water quality situation it has been said by the experts that the observed problem of taste, smell and colour of the treated water during the dry seasons, is due to a combination of many cause-effect relations, like high ammonia concentration → difficult to disinfect → not possible to control algae fully nor to ensure the hygienic quality of water → limitations of conventional treatment process [5].
The SWTP phase-I operational data show a clearly increasing trend of the monthly average and maximum values of ammonia, both increasing around three mg NH4-N/L over the four-year period from 2002 to 2006 [6]. Compared with the initial operating criteria for SWTP I of maximum 4 mg NH4-N per liter and with the Bangladesh Standard for Nitrate of 10 mg NO3-N, the increases are substantial in such a short period and the trend must be taken into consideration [6].
During formulation of SWTP phase-II project with the idea of pre-treatment of raw water, three probable options were discussed, namely: Stripping of ammonia, breakpoint chlorination, nitrification and de-nitrification, if needed. The experts proposed Moving Bed Biofilm Reactor (MBBR), prior to conventional treatment chain, as an option of pre-treatment which might be an economic and effective treatment process to remove pollutants from raw water [69].
The MBBR, first invented by Prof. Hallvard Ødegaard at Norwegian University of Science and Technology and was developed (Eur. pat. no. 0575314, US pat. no. 5,458,779) in the late 1980s, in Norway on the basis of conventional activated sludge and bio-filter process [10]. Quite large numbers of literature are available on the use of biofilm reactor for the treatment of wastewater [1119]. There are presently more than 400 large-scale wastewater treatment plants based on this process in operation in 22 different countries all over the world [13]. However, this innovative biofilm reactor has not been introduced for the pre-treatment of drinking water [19]. There is very little information in the literature on the use of biological drinking water treatment particularly on the use of MBBR [2024]. It has been said that “Biological filtration has not been historically accepted, at least not in North America” [21].
With such backdrops, before taking the crucial and revolutionary decision of a full-scale biological pre-treatment unit for a drinking water plant in Dhaka to mitigate pollution load of drinking water, a pilot study was conducted as a feasibility with a laboratory scale MBBR to pre-treat the raw water of the Sitalakhya River, the source raw water of the largest treatment plant in the country [25].

1.1. Objective of the Study

The objective of the present study is to investigate primarily the rate of reduction of raw water ammonia and the specific operating conditions of a particular source in a specific site using the Meteor pilot, as it is named, a biological pre-treatment system, which is a laboratory scale MBBR. It was intended to get some notions regarding its potential, as indicated by some manufacturer, in providing a tangible & sustainable solution to those difficult challenges encountered in Dhaka water. Reduction of COD and raw water oxygen demands were also evaluated in detail. The outcome of this study would be very useful and fundamental data for the design of future water supply project in Dhaka taking the Sitalakhya River water as the raw water source given that this biological process appears to be potential at this location. The other factors those affect the efficacy of a biological treatment like time since start-up, temperature, pollution loading rate, oxygen level required, resulting oxygen in the pre-treated water, hydraulic retention time (HRT), pH, sudden shock of pollution loading (like the increase in ammonia load from 0.5 mg NH4+/L to 6–10 mg corresponding to an increase in load of a factor 12–20 within a month), etc. were also noted.

2. Materials and Methods

2.1. Experimental Setup (Meteor Pilot Unit)

A pilot scale MBBR known as Meteor was used to investigate the feasibility of biological pretreatment of Sitalakhya River water. The pilot was built in a circular cylindrical shape reactor having a diameter of 400 mm & height of 1,200 mm as well as an effective volume of 100 L and made of transparent plastic (Fig. 2).
The study was carried out in the water testing laboratory of SWTP. The raw water was taken from the intake point of SWTP and the water testing facility in the SWTP laboratory was utilized for the study from February 9 to June 9 in 2011.
The laboratory scale Meteor pilot with a nominal volume of 100 L was filled with 50 liters of the ‘Meteor 660 media’ as it is called (Fig. 2 & 3). The description of prime characteristic features of media are as follows: the shape is corrugated cylindrical with colour black, the surface area of the media is 650 m2/m3, nominal diameter and length is 12 mm, bulk density 146 kg/m3, filling rate 50%, material is a high density poly ethylene, the specific gravity is 0.95. The reactor is equipped with one Flexazur fine bubble aeration tube (length: 35 cm) (Fig. 2), a raw water inlet pipe and a treated water effluent pipe fitted with a media retention screen (Fig. 3). The aeration is located on one side at the bottom of the reactor to create a spiral flow and thus provide primary function of oxygen transfer and mixing to ensure a full utilization of the reactor volume by making each small element in the media following the circulation of the waterand a uniform dispersion of dissolved oxygen throughout the mixed liquor of the reactor. The raw water coming from the inlet of the water treatment plant is pumped at a controlled rate into the bottom of the reactor, and the effluent leaves the reactor through the media retaining screen and flows by gravity to a drain in the laboratory. The range of flow rate was controlled from 0.5 to 2.0 L/min, with a few excursions to slightly higher flows (3.0 L/min). A flow rate of 2.0 L/min corresponds to the targeted full-scale Meteor design hydraulic retention time of 50 min. Compressed air is fed to the diffuser at rates from 6 to 40 L/min, depending on the loading rates and dissolved oxygen measurements. No external organic source other than the feed water was added in the pilot from outside. The average concentration of sulfide and phosphate in the raw water during the study was found to be 0.04 mg/L and 0.53 mg/L, respectively. The concentration of expected major quality parameter of the raw water are as follows, NH4/N: (10–15 mg/L), COD: (20–60 mg/L), BOD: (15–40 mg/L), Turbidity: 15 mg/L, pH: (6.5–8.5), DO: (1–3 mg/L), NO3: (0.2–4.2 mg/L), PO4: (0.3–4.9 mg/L), sulfide: (6–25 mg/L), Temperature: (20–30°C) and the targeted pre-treated raw water ammonia concentration is < 4 mg/L. The operating condition is briefly presented in Fig. 4 through Fig. 10.

2.2. Water Testing and Laboratory Analysis

The water quality investigation was performed in the water testing laboratory of SWTP. Some supplementary analysis was done in the laboratory of Civil Engineering Laboratory of Bangladesh University of Engineering and Technology, Bangladesh. The internationally accepted methods of sampling and testing like APHA were used in the investigation, for example ammonia was tested by using HACH DR 6000 spectrophotometer (HACH LANGE, USA) & Nessler method, No. 8038; COD was tested using HACH DR 890 colorimeter (HACH LANGE, USA), HACH DRB200 COD reactor (HACH LANGE, USA) & by reactor digestion method No. 8000, Turbidity was measured using HACH 2100Q Turbidity meter (HACH LANGE, USA) & by nephelometric method, etc.

3. Results and Discussion

3.1. Start-up Period

The pilot unit operation started on February 9, 2011, at a feed flow rate of 0.5 L/min (HRT = 3.3 h), with a process air flow rate of 6 L/min, which was sufficient to provide adequate mixing & transfer of oxygen. Progressively the nitrification process began and the effluent ammonia concentration decreased to below 2.0 mg NH3-N/L within 12 d. Thus the nitrification biofilm was developed on the media and the process established within a period of two weeks. By March 06 the pilot was operating consistently at the design flow of 2.0 L/min.
The process air was also increased progressively from 6 to 12 and eventually up to 30 L/min [4]. The immediate response to the increased air on March 08 was a decrease in the effluent NH3-N to < 4.0 mg/L, demonstrating that the oxygen was a limiting factor for the initial days when running at the design water flow rate of 2.0 L/min. The intended removal of 11 mg NH3-N/L was achieved by 27 d of operation when there was sufficient oxygen for the process [Fig. 5]. Overall, the required time to achieve the maximum targeted ammonia removal rates is less than four weeks, and if sufficient air would have been provided the required time might be less, in the order of three weeks.
In general, the start-up of the Meteor process will coincide with the beginning of the dry-season at Dhaka, which will occur at the beginning of December, and the raw water ammonia concentrations expected to be in the range of 2 to 4 mg/L and progressively increase to 6 to 8 mg/L during a period of eight weeks. The results from the pilot study show that starting with virgin media the process will be able to follow this increase in ammonia loading. For a situation where the process needs to start in the middle of the dry-season (high ammonia concentrations > 10 mg/L), the process can be expected to reach design removal rates after a period of approximately three weeks.

3.2. NH3-N Removal

During the initial period, after the start-up was achieved, the Meteor was able to remove 11 mg/L at the design flow (Fig. 6). During the period from March 29 through May 5, the pilot run at 2.0 L/min (except for days when there were issues with the feed flow control) and the raw water ammonia concentrations are found in the upper range: 10 to 17 mg/L. This period demonstrates the full capacity of the process, with average removed ammonia of 11 mg/L, and a maximum removal of 13.5 mg/L. During this period the effluent NH3-N is maintained below 4.0 mg/L (excluding the days when feed flow rate is > 2.0 L/min), with an average effluent NH3-N of 1.7 mg/L (excluding days when feed flow rate is not 2.0 L/min) (Fig. 6). The organic concentration (cBOD, soluble cBOD) in the raw and pretreated water is shown in Fig. 7. The dissolved oxygen concentrations in the feed and effluent water are shown in Fig. 8. During the pilot study, the influent strength was NH3-N > 15 mg/L for 20 d, and the amount of NH3-N removed was > 11 mg/L for 42 d.

3.3. COD Removal and Raw Water Oxygen Demand

The raw water total COD varied significantly during the study, from 10 mg/L to 80 mg/L (Fig. 9), with similar general trends in the variation of concentration as the ammonia. The average ratio of soluble/total COD in the raw water is 79%, which is higher than typical for municipal wastewaters.
The COD removal based on the influent total COD minus the effluent soluble COD provides a calculation of the maximum amount of carbonaceous pollution removed in the Meteor pilot unit. It also represents the maximum overall oxygen consumed for the oxidation of pollutants in the raw water other than ammonia. Fig. 9 shows the total raw water COD, effluent soluble COD and a calculated COD removal (the difference between these two values) during the period when these analyses were made. During the period from 12 April through 21 May, the COD removal was in a range from 13 to 52 mg/L, with 4 d having COD removal in the range from 30 to 50 mg/L. Thus the biological process was able to remove more carbonaceous pollution than the feasibility report and at the same time remove the required ammonia load. It is notable that there still remains 10 to 40 mg/L of soluble COD which is not removed by the biological treatment because this fraction of the COD is non-biodegradable. The very high ratio of COD/BOD in the raw water (5 on average) also indicates that the water is not very biodegradable. Therefore, the results demonstrate that there are also some forms of dissolved pollution present in the raw water which cannot be removed by biological treatment.
These results show that the oxygen demand of the raw water (not including the ammonia oxygen demand) exceeds the limit of 30 mg/L indicated in the feasibility study [5]. Since the measured levels of sulfide in the raw water were insignificant, this means that the level of carbonaceous pollutants is higher than expected. The results also show that oxygen demands will be higher than 30 mg/L for carbonaceous pollutants during periods of peak pollution coinciding with the peak ammonia concentrations. No significant level of sulfides was found in the raw water or treated water, therefore the target of < 0.1 mg/L S2-/L in the effluent was easily achieved. A comparison of the actual oxygen consumed in the pilot study (due to both COD and ammonia removal) and the estimated oxygen demand value for the Meteor process demonstrate that during the peak pollution period in April 2011 the raw water exerted a higher oxygen demand than the targeted full-scale design. Noted that the full-scale design oxygen demand, based on the feasibility study, is 75 mg/L (30 mg/L for carbonaceous pollutants and sulfides + 45 mg/L for ammonia removal) [5]. Fig. 10 plots both the COD and ammonia removal during the period of April 11 through the end of the study, including the total oxygen consumption values based on: mg/L COD removed + 4.57 × mg NH3-N/L.
Seven days surpass the maximum expected value of 75 mg/L of oxygen and reach a maximum value of 99 mg/L. No similar COD data is available for the largest pollution peak in March; however during the periods of raw water ammonia concentrations above 15 mg/L the oxygen demand (to remove the COD and the ammonia down to 4.0 mg/L) will be above the expected 75 mg/L. During these periods, the aeration will be a limiting factor and may not allow the removal of more than the design ammonia load.

4. Conclusions

A laboratory scale pilot MBBR, called Meteor pilot, was used for biological pre-treatment of Sitalakhya raw water in this study. The targeted removal of 11 mg/L of ammonia was possible with an air feed of 40 L/min. It took three weeks to fully develop the system and full scale start up since commissioning. At the beginning the ammonia concentration was low with low removal rate. Along with ammonia the process can remove COD also from the raw water. But COD will compete with the ammonia. There must be provision of adequate time in the full scale treatment plant for necessary time to establish the nitrification process to start up fully. It will be risky in the context of quality to start the pre-treatment at the middle of the dry season with high ammonia content in raw water. The period of high ammonia in the raw water coincides with the period of high COD demanding more oxygen than anticipated for ammonia alone. During the periods when the oxygen supply is a limiting factor, due to the probable excessive pollution in the raw water, the following negative impacts on the biological process performance and WTP are likely to occur:
  • The ammonia in the pretreatment effluent will be > 4.0 mg/L, thus overloading the chlorination capacity of the WTP. An unstable nitrification process due to ammonia overloading, and lack of oxygen, will produce nitrite NO2N, which will exert a chlorine demand and overload the chlorination capacity of the WTP.

  • Excessive residual soluble COD pollution will not be removed in the WTP and can interfere with the operation and performance of the WTP.

  • As expected, during the periods of peak ammonia concentration in the raw water, the amount of ammonia nitrified and thus nitrate produced would be > 10 mg NO3-N/L, exceeding the nitrate standard for drinking water.

  • The raw water at Saidabad seems to have a fairly high alkalinity – especially during the dry season (150–250 mg/L). It is therefore unlikely that addition of chemicals becomes necessary.

Pre-treatment would be an option, but not an ideal one, since the removal of organic matter and sulfide needs to be done simultaneously and de-nitrification will soon be needed in the process. The economic & financial analysis including the opportunity cost of the total system should be assessed as a part of the feasibility.
Pollution control, in the long run, is the optimal solution for Dhaka water in all respect.

Acknowledgments

A number of advisers and technical personnel were involved in the development & implementation of the biological nitrification pilot plant from M/s Degremont of France and this cooperation is greatly appreciated.

References

1. Serajuddin M, Rahman MM. Sustainable water supply: A tale of a megacity. In : International Symposium on Environmental Degradation and Sustainable Development ISEDSD 2010; 10–11 April 2010; BUET, WEDC, British Council.


2. Serajuddin M. Issues and challenges of water supply for a safer megacity - perspective Dhaka. In : National Seminar on Engineers Role in Developing a Safer Megacity; 20 December 2009; Dhaka Centre, the Institution of Engineer’s, Bangladesh.


3. IWM. Assessment of the water quality of Lakhya River with special reference to the intake point of Saidabad water treatment plant. Draft Final Report. 2005.


4. Serajuddin M. Water Treatment at Saidabad Plant: State-of-the Art. ‘Engineering News’ Institution of Engineers, Bangladesh (IEB). 28(4)July–August 2002;


5. DWASA. Joint feasibility study of pre-treatment for water supply for the Saidabad water treatment plant, Dhaka, Bangladesh, Conducted by Grontmij/CarlBro, Final Report. 2007.


6. Serajuddin M. Issue of raw water quality in the treatment of drinking water at Dhaka. In : Proceedings of the ICETCESD 2011; SUST, Bangladesh. 2011.


7. Pastorelli G, Andreottola G. Pilot plant experiments with moving bed biofilm reactors. Water Sci Technol. 1997;36:43–50.


8. Rusten B, Siljudlen JG, Strand H. Upgrading of a biological-chemical treatment plant for cheese factory waste water. Water Sci Technol. 1996;34:41–49.


9. Aspegren H, Nyberg U, Andersson B, Gotthardsson S, Jansen JC. Post denitrification in a moving bed biofilm reactor process. Water Sci Technol. 1998;38:31–38.


10. Ødegaard H, Rusten B, Westrum T. A new moving bed biofilm reactor – Applications and results. Water Sci Technol. 1994;29:157–165.


11. Ødegaard H. Innovations in wastewater treatment: The moving bed biofilm process. Water Sci Technol. 2006;53:17–33.
crossref

12. Chen S, Sun D, Chung JS. Simultaneous removal of COD and ammonium from landfill leachate using an anaerobic-aerobic moving-bed biofilm reactor system. Waste Manage. 2008;28:339–346.
crossref

13. Rusten B, Eikebrokk B, Ulgenes Y, Lygren E. Design and operations of the Kaldnes moving bed biofilm reactors. Aquacult Eng. 2006;34:322–331.
crossref

14. Gulhane ML, Kotangale AJ. Moving bed biofilm reactor – New innovation in the field of conventional biological wastewater treatment. Int J Sci Res. 2013;2:54.
crossref

15. Stuart Palmer. Report on research literature related to moving bed biofilm reactor wastewater treatment. Deakin University; Waurn Ponds, Vic.: March 2013.


16. Ahmadi M, Alavi N, Jaafarzadeh N, Ghaedrahmat Z, Hashemi F. Performance evaluation of moving bed bio film reactor in saline wastewater treatment. Iran J Health Sci. 2013;1:58–64.
crossref pdf

17. Qiqi Y, Qiang H, Ibrahim HT. Review on moving bed biofilm processes. Pakistan J Nutr. 2012;11:706–713.
crossref

18. Kermani M, Bina B, Movahedian H, Amin MM, Nikaein M. Application of moving bed biofilm process for biological organics and nutrients removal from municipal wastewater. Am J Environ Sci. 2008;4:682–689.


19. Xie SG, Tang XY, Wu WZ, Wen DH, Wang ZS. Biological pre-treatment of Yellow River water. J Environ Sci (China). 2005;17:557–561.
pmid

20. Evans PJ, Opitz EM, Daniel PA, Schulz CR. Biological drinking water treatment perceptions and actual experiences in North America. Water Research Foundation and Department of Defense; Washington D.C., USA: 2010.


21. Takó S. Ammonium removal from drinking water – Comparison of the breakpoint chlorination and the biological technology. In : Conference of Junior Researchers in Civil Engineering; 2012.


22. Bouwer EJ, Crowe PB. Biological processes in drinking water treatment. J Am Water Works Assoc. 1988;80:82–93.
crossref

23. Rittmann BE, Snoeyink VL. Achieving biologically stable water. J Am Water Works Assoc. 1984;76:106–114.
crossref

24. Lytle DA, Williams D, Muhlen C, et al. Engineering design and operation report: Biological treatment process for the removal of ammonia from a small drinking water system in Iowa: Pilot to full-scale. USEPA; 2014. Sept EPA/600/R-14/336 | September


25. Serajuddin M. Biological pre-treatment of the Sitalakhya River water at Dhaka: A pilot study on ammonia removal. In : Proceedings of the ICACE 2012; CUET, Bangladesh. 2011.


Fig. 1
Raw water source and its transmission network from Sitalakhya River to WTP.
/upload/thumbnails/eer-23-2-136f1.gif
Fig. 2
Experimental setup of Meteor pilot unit & flow diagram.
/upload/thumbnails/eer-23-2-136f2.gif
Fig. 3
Meteor 360 media, pilot effluent pipe with media retaining screen.
/upload/thumbnails/eer-23-2-136f3.gif
Fig. 4
Weekly average of feed, air flow & hydraulic retention time (HRT) in the reactor.
/upload/thumbnails/eer-23-2-136f4.gif
Fig. 5
Ammonia concentrations during start-up.
/upload/thumbnails/eer-23-2-136f5.gif
Fig. 6
Influent and effluent NH3-N concentration & feed flow during study.
/upload/thumbnails/eer-23-2-136f6.gif
Fig. 7
Weekly average of nitrate, nitrite, total cBOD & sol.cBOD in the influent & effluent.
/upload/thumbnails/eer-23-2-136f7.gif
Fig. 8
Weekly average of pH, temperature, DO & turbidity in the influent and effluent.
/upload/thumbnails/eer-23-2-136f8.gif
Fig. 9
COD removal.
/upload/thumbnails/eer-23-2-136f9.gif
Fig. 10
Oxygen consumption, COD & ammonia removal.
/upload/thumbnails/eer-23-2-136f10.gif
TOOLS
PDF Links  PDF Links
PubReader  PubReader
Full text via DOI  Full text via DOI
Download Citation  Download Citation
  Print
Share:      
METRICS
1
Web of Science
1
Crossref
0
Scopus
6,634
View
133
Download
Editorial Office
464 Cheongpa-ro, #726, Jung-gu, Seoul 04510, Republic of Korea
FAX : +82-2-383-9654   E-mail : eer@kosenv.or.kr

Copyright© Korean Society of Environmental Engineers.        Developed in M2PI
About |  Browse Articles |  Current Issue |  For Authors and Reviewers